When do I need to call for green inspection?
Call for initial inspection after HVAC is installed and ducts sealed and prior to drywall installation.
Call for initial inspection after HVAC is installed and ducts sealed and prior to drywall installation.
Guest rooms in a hotel for sleeping purposes and any related use is considered a residential project.
Contact the designated plan checker on your project to make an appointment for verification of corrections. Contact information is provided on the correction sheet. Approval for Green Building requirements will be provided after verification of all corrections is completed.
The report can be prepared by commissioning agents and any other trained personnel with experience on projects of comparable size and complexity.
The manufacturer’s website will usually have this information readily available. Alternatively, the Cool Roof Rating Council (CCRC) provides a searchable public database for all products that have been tested by the organization.
Ducts should be covered as soon as installed, and shall remain covered until the HVAC system is installed and ready to be turned on.
Commissioning report is required for all new non-residential projects of 10,000 square feet or more. The exceptions are warehouses, open parking garages and similar projects.
No, EV charging stalls are required to be unrestricted and available for all users. However, if the EV charging infrastructure is located in a manner where it can facilitate both spaces, then it will be acceptable.
Green Building code is applicable to the following projects:
No, the number of stories does not change the requirements of a residential or non-residential use.