What information sources will the City use to determine what existed on my lot before the fire? What if there is different information in my old building permits compared to other sources such as the County Assessor?
Acceptable records shall include building permits, Certificate of Occupancy, County Assessor, and Coastal Commission. On a case by case basis, the Department may consider other photographic sources such as Google Maps and LiDAR.
What is the timeline for DBS to review a plan and issue a permit?
Under the Mayor’s Emergency Executive Order #1, DBS and other City departments will complete their initial reviews for building permits within 30 days. However, DBS has so far been able to complete the review within 10 days.
How will the foundation be established for the rebuild after it is removed?
If the foundation was removed, LADBS would use available records to establish where the footprint of the foundation was originally. Please see question above regarding what records LADBS will use to establish what was on a site prior to the wildfire.
How will LADBS review my project if I cannot find copies of my original building plans, including plans for my foundation?
LADBS would use available records to establish what was on a site prior to the wildfire. New building plans would then need to be prepared and submitted to the Department for review.
Can I build a new ADU as part of my rebuild project? Can the ADU be built before the main house?
Yes, a new ADU can be built as part of the rebuild and still qualify as a like-for-like +10% project per the Governor's Directive No. N-20-25, regardless of whether or not an ADU existed on the site prior to the Wildfire.