Can I request a different inspector?
Inspectors are assigned by district, with a few exceptions.
Can I start work before I obtain my permit?
No, work cannot be started until a valid permit is issued.
Can you obtain an special event permit online?
Yes, all special event permits are issued online.
Do I have to pay for a Certificate of Occupancy?
The fees are a part of the inspection fees.
Do I have to return to plan check for all changes?
Minor changes usually do not require returning to plan check. All major or structural changes require you to return to plan check.
Do I have to return to the plan checker who reviewed my plans for corrections?
No, but it would be more helpful if the plan checker was the original one who granted approval.
Do I have to schedule a different inspection for each division?
Yes. Each division has their own permit.
Do the inspectors work weekends for special events?
Yes, staff work days include Saturday and Sunday.
How are the fees calculated for a TCO?
The fees are calculated by the type of occupancy.
How can I schedule an off-hour inspection?
Off-hour inspections can only be scheduled through the LADBS.org website. You may schedule an off-hour inspection through our Online Services.
What is the cost of an off-hour inspection?
The fees for an off-hour inspection is $318.00.
How do I pay for an off-hour inspection?
Off-hour inspections can only be paid through the LADBS website.
How late can I schedule an inspection?
You can schedule an inspection for the next day, so long as you do so before 4:00 PM.
How long does it take to process the certificate of occupancy.
Anywhere between 1 to 7 days.
How many inspections can I have with this permit?
Depending on the project, there could be one or as many as needed to complete the project.
How many inspectors will I have in residential?
One inspector for building, electrical, plumbing, HVAC, grading, and green. Separate for Fire Sprinkler.
How many stories can the building be?
Based on the height district and the type of construction, the building can be single-story to unlimited.
How much are non-compliance fees?
Fees are $550.00 for failure to comply within 15 days of the compliance date.
Information on my permit is incorrect. How do I get it corrected?
The inspector will issue to the correction for you to return to plan check and correct the error.
Is there a fee for a duplicate copy of the permit card?
If the customer misplaces the permit, then yes. For department errors, there is no fee.