Sites in most hillside areas, within potentially liquefiable zones, where infiltration rates are too low, or where the earth materials exhibit adverse conditions when saturated (e.g., expansive or hydro collapsible soils) are generally not allowed to infiltrate stormwater.
A fault investigation is required if the project is located within an Alquist-Priolo Earthquake Fault Zone or a Preliminary Fault Rupture Study Area to preclude construction for human occupancy from being placed on an active fault.
Why must I have a sump pump with a backup generator?
The Department requires the use of a back-up generator for sloping properties to maintain proper drainage and reduce the potential for erosion and sloughing in the event of a power failure.
Can the electric vehicle (EV) charging infrastructure provided at a disabled parking stall be used to satisfy the Green Building requirements?
No, EV charging stalls are required to be unrestricted and available for all users. However, if the EV charging infrastructure is located in a manner where it can facilitate both spaces, then it will be acceptable.