Building Research Section (BRS)
The BRS approves alternate building materials or products that are at least equivalent to the materials prescribed in the code in terms of quality, effective time period of fire resistance, strength, effectiveness, durability and safety.
Additional Information
Approved materials are published as Los Angeles Research Reports (LARR).
The Building Research Section is located at our Metro location (201 N Figueroa St, Rm 880, Los Angeles, CA 90012)
LA Research Reports (LARR)
LADBS approves alternate building materials or products that are at least equivalent to the materials prescribed in the code in terms of quality, effective time period of fire resistance, strength, effectiveness, durability and safety.
Approved materials are published as Los Angeles Research Reports (LARR).
Additional Resources
- FAQ
- Applications
- Publications
FAQ Search Results
Filtered categories:
All
How long does it take to process the certificate of occupancy.
Anywhere between 1 to 7 days.
How long does take to assign my plan to a plan check engineer?
The time to assign the plans changes from week to week. Normally, regular plan check submittals take 15 to 30 business days, and expedite submittals will take 6 to 10 days. These estimates are subject to change.
How long does the evaluation process take?
The initial evaluation process will take about 2 to 4 weeks. The overall completion of the evaluation and approval depends on the applicant.
How long do I have to wait for a Demolition Pre-Inspection (DPI)?
A DPI normally takes two weeks minimum to be prepared.
How long do I have to wait for a Grading Pre-Inspection to be completed?
A Grading Pre-Inspection normally takes two weeks, but it could be longer.
How long do I have to wait for a Sign Pre-Inspection (SPI) to be completed?
It normally takes minimum of two weeks for a Sign Pre-Inspection (SPI) to be completed.
How long do I have to wait to hear a response to my appeal?
It normally takes 45 days from the time your appeal is submitted to LADBS. See the Information Bulletin P/ZC 2023-019 for more information.
How long do I need to wait for Health Department approval?
You will need to check with LA County Health Department. It is recommended that you submit plans to the health Department as soon as you can. It may take few months to obtain your approval.
How long is a plan check application good for?
Plan check applications expire 18 months after the plan check fees are paid. However, within 30 days of its expiration, an extension of time to extend a permit application may be filed with the Department using a Request for Modification of Building Ordinances. The request may be filed with any Plan Check office, preferably with the office where the plan was reviewed. A fee shall accompany each request.
How long is a soils/geology report good for?
In general, four years, unless there is a change in the scope of work or adoption of a new LABC.